Nordic data centres

Two items, from 6 Oct 2026 to 9 Nov 2026, oldest first.

See also: Point 4 of our view: Scarce capital, power and sites

Policy

Finland orders Google to halt work at two data-centre sites (6 Oct) by 23 Oct, pending environmental assessment

Finland's supervisory agency ordered Google's local company to stop site preparation in Muhos and Kajaani, where 330 and ~200 hectares of forest were cleared before the required environmental assessment; the sites are part of a planned €13bn project. Google said it had fallen short of its own standards.

Why it matters. Land, power and permits, not the machines, are what limit how fast AI data centres can be built, and Finland has just shown it will use them.

Next. Google's deadline to stop work is 23 October.

Sources: yahoo.com, news.google.com

Policy

Norway's grid operator Statnett halts new data-centre connection bookings (9 Nov); 26,000 MW sought this year

Statnett has suspended further reservations of grid capacity for data centres until a government licensing scheme is in place, expected by 1 August 2027 at the latest. Connection applications this year total 26,000 MW, 75% from data centres, against a national peak load of about 25,000 MW; 800 MW is connected, 4,200 MW reserved and 9,100 MW queued.

Why it matters. Norway has stopped booking grid capacity for new data centres after requests for new connections exceeded the country's entire peak power demand. If other countries with spare power follow, the AI build-out could perhaps be slowed less by money than by electricity, and the owners of sites already connected might capture much of the value.

Next. Norway's licensing scheme for data centres, due before the pause ends by 1 August 2027.

Sources: cyprus-mail.com, devdiscourse.com · Point 4 of our view · Context: not counted as evidence